Instead of Repairing the Cracked Patio, They Removed the Concrete and Started Building a Deck
  1. Homedit
  2. How To, Tips, and Advice

Instead of Repairing the Cracked Patio, They Removed the Concrete and Started Building a Deck

Brittney and her family decided to replace a cracked backyard patio that had developed drainage problems and settlement issues. Large cracks had spread across the concrete, and one section collected water during rainstorms, directing moisture toward the foundation.

Instead of Repairing the Cracked Patio, They Removed the Concrete and Started Building a Deck

Rather than patching the surface or pouring a new slab, they decided to remove the concrete completely and start over. The plan called for a low backyard deck, but before any framing could begin, every section of the existing patio had to come out.

Concrete Removal Started Near the House

Concrete Removal Started Near the House

Patio replacement began with a cracked concrete slab that had developed drainage problems over time. Water collected near the house after storms, and several sections showed settlement, patching, and long fracture lines.

Best Way to Remove Concrete Slabs on a Patio

Work started along the foundation where the first section could be separated from the remaining patio. Using a pry bar, sledgehammer, and lift jack, the family created an opening beneath the slab and began breaking the concrete into smaller sections.

full extent of the patio footprint

As demolition continued, larger sections of the patio were removed and the site was cleared for grading. Once demolition was complete, the site was ready for footings and framing.

Deck Framing Started Around the Existing Steps

Deck Framing Started Around the Existing Steps

With the concrete patio removed, construction shifted to the structure that would support the new deck. The curved concrete steps remained in place, so the perimeter frame was built around them rather than removed and rebuilt.

Pressure-treated framing lumber established the outline of the future deck and connected the support posts installed during the previous stage. Multiple boards were fastened together to create stronger perimeter beams capable of supporting the deck surface and furniture loads.

Careful measurements around the curved stair profile allowed the framing to follow the shape of the existing entrance. With the perimeter established, the footprint of the future deck became visible.

Footing Locations Were Marked Before Construction

Footing Locations Were Marked Before Construction

With the patio removed and the deck layout established, attention shifted below ground. Support locations were marked across the site, and holes were dug where the deck frame would eventually transfer its weight to the ground.

Concrete forms were placed into the excavated holes and aligned using string lines stretched across the future deck footprint. Those reference lines kept each footing in position and ensured the framing installed later would remain square and consistent.

Once the forms were aligned, pressure-treated posts were set into fast-setting concrete and checked for position before the mix hardened. Once the concrete cured, the first permanent supports were in place for the deck and pergola structure.

Deck Perimeter Started Defining the New Space

Instead of Repairing the Cracked Patio, They Removed the Concrete and Started Building a Deck

Pressure-treated framing boards were attached to the support posts and extended around the outer edge of the future deck. Double 2×6 members created a stronger perimeter capable of supporting both the deck surface and the pergola structure planned above.

The curved concrete steps remained in place, so the framing followed their shape rather than forcing a straight edge across the front of the house.

The perimeter framing connected the support posts into a single structure and established the outer edge of the future deck.

Framing Turned Individual Posts Into One Structure

Instead of Repairing the Cracked Patio, They Removed the Concrete and Started Building a Deck

Additional framing sections completed the outer border and tied the pergola posts into the deck foundation. Careful measurements, level checks, and lag-bolt connections kept each section aligned across the entire footprint.

What began as scattered footings and isolated posts now functioned as a unified frame. The layout defined the final deck shape, established support points for future joists.

Joists Filled the Frame With Structural Support

Instead of Repairing the Cracked Patio, They Removed the Concrete and Started Building a Deck

After the perimeter framing was complete, joist hangers were installed at 16-inch intervals along the frame. Those brackets established the spacing for each joist and created a consistent support system across the entire deck footprint.

Pressure-treated 2×6 joists were cut to length and secured between opposing brackets. Where support posts interrupted the layout, the framing was adjusted to maintain structural continuity without disrupting the spacing pattern.

Each joist increased the rigidity of the frame and helped distribute weight across the beams and footings.

all deck joists installed

Support posts, perimeter framing, beams, and joists now worked together as a single structure.

With the joists installed, the structural framework was complete and ready for decking.

Redwood Deck Boards Covered the Structure

Instead of Repairing the Cracked Patio, They Removed the Concrete and Started Building a Deck

Redwood decking boards were installed across the joists, starting at the house and moving toward the yard. Chalk lines and spacers kept the rows straight and maintained consistent gaps between boards.

Hidden fasteners secured the boards to the framing below, creating a clean surface without exposed screw heads.

Instead of Repairing the Cracked Patio, They Removed the Concrete and Started Building a Deck

Openings were cut where the decking met concrete steps, pergola posts, and utility lines. Each board was trimmed to fit while maintaining the spacing and alignment established across the rest of the deck.

Instead of Repairing the Cracked Patio, They Removed the Concrete and Started Building a Deck

As more boards were installed, the framing disappeared beneath the new surface. The former concrete patio became a redwood deck connected directly to the house and ready for finishing work.

Stain and Sealer Finished the Deck

Stain and Sealer Finished the Deck

The completed redwood deck was sanded, cleaned, and coated with a penetrating stain and sealer designed to protect the wood from moisture, sun exposure, and seasonal movement. Applying the finish after construction helped seal the surface while preserving the natural grain pattern of the boards.

As the stain absorbed into the redwood, the deck developed deeper color variation across the floor. Lighter and darker boards remained visible, giving the surface a natural appearance rather than a uniform painted finish.

Once the finish cured, construction was complete. What began as a cracked concrete patio had been rebuilt into a low redwood deck supported by new footings, framing, joists, and decking boards, creating a larger and more functional outdoor space.

Cracked Concrete Patio Became the Foundation for a New Outdoor Space

Cracked Concrete Patio Became the Foundation for a New Outdoor Space

The project began with a cracked concrete patio that had developed drainage problems and uneven sections over time.

Before concrete and after with deck

After the concrete was removed, new footings, framing, joists, decking boards, and pergola posts transformed the area into a redwood deck that followed the shape of the existing concrete steps while creating a larger usable surface.

Side by side cracked concrete and the new deck

Side-by-side photos show how the damaged concrete patio was replaced with a raised redwood deck built on new footings and framing.

Redwood Deck Wrapped Around the Existing Concrete Steps

Redwood Deck Wrapped Around the Existing Concrete Steps

Rather than demolishing the curved entry steps, the deck was built around them. The decking follows the shape of the concrete, allowing the original staircase to remain while integrating it into the new layout.

The before and after patio project finished

The deck extends across most of the former patio footprint and creates a continuous surface directly outside the sliding door.

The cutting deck around the curved stairs

One of the more complex parts of the project was fitting the deck around the curved concrete staircase. The finished edge follows the contour of the steps while maintaining consistent spacing and alignment across the deck boards.

The photos highlight the major stages of the build, from concrete removal and footing installation to framing, decking, and finishing. Between those milestones, measurements, cuts, adjustments, and inspections helped keep the structure level and aligned.

Would you have kept the original concrete patio and repaired it, or would you have started over with a deck like this one?